[CANCELLED] Electrical infrastructure – data center Digital Realty Business Park (AMS18) Amsterdam

Scheduled Maintenance Report for DC1.AMSTERDAM

Completed

The scheduled maintenance has been completed.
Posted Oct 13, 2026 - 17:00 CEST

Verifying

Dear Valued Customer,

The scheduled maintenance that was set to take place on 13 October 2026, 07:00–17:00 CEST has been cancelled by Digital Realty. The data center's electrical infrastructure will remain fully operational and available without interruption during this window.

We apologize for any inconvenience this may cause. We will share a new schedule as soon as a new date is confirmed.

If you have any questions regarding this maintenance, please contact our team at noc@dc1.amsterdam.

Kind regards,
Team DC1.AMSTERDAM
Posted Oct 12, 2026 - 17:48 CEST

Scheduled

Dear Valued Customer,

Scheduled maintenance work will take place on 13 October 2026, 07:00–17:00 CEST, involving the replacement of circuit breakers within the data center's electrical infrastructure. This preventive maintenance is performed every five years.

During the replacement work, the equipment load will be powered exclusively via the alternative power feed. As a result, the normal dual-feed configuration (feed A and feed B) will temporarily be unavailable, and electrical redundancy will be reduced for the duration of the maintenance.

Maintenance schedule 13 October 2026, 07:00–17:00 CEST:
Maintenance on power feed B (black PDU) - impact: NO POWER.
The alternative power feed will be feed A (yellow PDU).

We strongly recommend checking in advance that your equipment is connected to both available power feeds, feed A and feed B. Any equipment with only a single power connection must be connected to the designated alternative power feed to maintain power continuity during the maintenance work.

The single-feed condition will be - temporary and limited - to the time required to replace the circuit breaker and complete all necessary operational checks and verifications. Once the replacement circuit breaker has been installed, switched on and verified, the normal dual-feed configuration will be restored and full electrical redundancy will be available again.

We recommend that you take this temporary reduction in redundancy into account and implement any appropriate precautionary measures where necessary.

We apologize for any inconvenience this may cause and thank you for your understanding and cooperation.

Our team will be present on-site throughout the maintenance work to provide assistance if required.

-

We would like to apologize for the fact that this maintenance scheduled was not announced in a timely manner. During the preparation of this maintenance, the impact assessment was not carried out correctly, meaning that the potential impact on one of our zones at the Digital Realty Business Park (AMS18) data center in Amsterdam was not identified.

We have since discussed this with the data center and improved the impact assessment process to ensure that the potential impact on the different zones is better taken into account in future maintenance communications. We understand that timely and comprehensive maintenance communications are essential, and we regret that this was not the case on this occasion.

-

If you have any questions regarding this maintenance, please contact our team at noc@dc1.amsterdam.

Kind regards,
Team DC1.AMSTERDAM
Posted Oct 09, 2026 - 15:19 CEST
This scheduled maintenance affected: Data Centers (Colocation data center Business Park (AMS18)).